















 |
Offshore
Wind Energy: Full Speed Ahead
by
Soren Krohn
Managing Director
Danish Wind Turbine Manufacturers Association
Summary
Commercial sized offshore wind turbine
parks will become a reality in Denmark around the year 2000.
750 MW will be built in the first five to seven years of the
next century, with another 3300 megawatt planned to go on-line
in the years up to 2030, thus achieving a 50 per cent wind penetration
in the grid. The energy policy interest in wind energy in Denmark
is primarily based on its ability to deliver large volume CO2
reduction from power generation cheaply.
Shortage
of land sites in north-western Europe is one reason for this
move offshore. Other reasons include significantly higher wind
speeds than on land, and thus higher energy production at sea.
In addition, new research results indicate that wind speeds at
sea are higher than what was previously estimated. The marine
environment gives more stable winds with less turbulence and
less wind shear, facilitating the design of cheaper turbines
with a longer lifetime.
To
be economic, offshore wind parks have to be large (120 to 150
MW), and use large turbines (1.5 MW and above). New foundation
technologies, using steel rather than concrete has improved the
economics of offshore wind power dramatically. Wind turbines
at sea would have a longer design lifetime due to lower mechanical
fatigue loads. If this is taken into account, energy costs per
kWh may be as low as 4 US cents per kWh, although more conservative
estimates point to 5 US cents/kWh using present day technologies.
Other
than decreasing installation costs even further, technical challenges
are abundant in this frontier line of wind technology. Logistics
and grid integration will pose interesting problems, and phasing
up to 50 per cent wind into the Danish electricity grid, will
mean a longer term redesign of grid technology in the direction
of a more flexible, decentralised system with large amounts of
CHP and heat storage, plus a more co-ordinated use of wind and
the neighbouring countries' hydro resources.
From
an environmental point of view offshore wind parks have few drawbacks.
A new scientific study has shown that wind parks at sea have
no significant influence on bird life. A life-cycle calculation
of energy use in manufacturing, deployment and maintenance of
an offshore wind park by the author shows that the energy thus
consumed is less than 2.5 per cent of the energy produced by
the park, thus making wind energy one of the cleanest generating
technologies available.
1.
Introduction
More than 4,000 megawatts (MW) of wind power may be installed
offshore in Denmark in the course of the coming 30 years. Larger
wind turbines, cheaper foundations, and new research on offshore
wind conditions are boosting the confidence of both power companies,
government, and turbine manufacturers.
While
wind energy is already economic in good onshore locations, wind
energy is about to cross another frontier: The economic frontier
set by shorelines. Danish researchers and developers are about
to challenge conventional wisdom on electricity generating technologies:
With future costs around 4 to 5 US cents per kWh, offshore wind
energy is rapidly becoming competitive with other power generation
methods.
Two
offshore pilot wind farms of 5 MW each have been built in Denmark
by the electric utilities using conventional wind turbines: Vindeby
in 1991 and Tunoe Knob in 1995. Two semi-offshore projects, in
the extremely shallow waters of the Ijselmeer have been built
less than 100 metres off the coasts of the Netherlands. The latest
project, consisting of 19 Danish 600 kW wind turbines was commissioned
in 1996. Another project with five Danish 600 kW wind turbines
was commissioned at the end of 1997 South of Gotland, Sweden.
All of these projects are smaller scale pilot projects, with
costs substantially above the figures indicated above.
Future
projects are likely to be much larger, however, due to economies
of scale.
2.
Reasons for Going Offshore
2.1
Land Sites in Short Supply in Some Countries
One of the primary reasons for moving wind farm development offshore
is the lack of suitable wind turbine sites on land. This is particularly
the case in densely populated countries like Denmark or the Netherlands
with a relatively flat landscape.
2.1
Higher Wind Speeds
Equally important, however, is the fact that wind speeds are
often significantly higher offshore than onshore. An increase
of some 20 per cent at some distance from the shore is not uncommon.
Given the fact that the energy content of the wind increases
with the cube (the third power) of the wind speed, the energy
yield may be some 73 per cent higher than on land. Economically
optimised turbines, however, will probably yield some 50 per
cent more energy at sea than at nearby land locations. (Bear
in mind, that since the fuel is free, economically optimal wind
turbines will generally have capacity rates as low as 25 to 30
per cent).
In
countries like the UK, however, the difference between good land
sites and offshore sites may be smaller or nil, since turbines
on land are often situated on hilltops where the wind speeds
up significantly compared to the speed in flat terrain.
2.2
More Stable Winds
It is a frequent misunderstanding that wind power generation
requires very stable winds. In most wind turbine sites around
the globe, in fact, the wind varies substantially, with high
winds occurring rather infrequently, and low winds occurring
most of the time.
If
we look at the typical statistical wind distribution, most of
the energy output is in fact produced at wind speeds close to
twice the average wind speed at the site. In addition, in e.g.
Europe and a number of other locations around the globe wind
speeds happen to be positively correlated with peak electricity
use (more wind during the day than at night, more wind in winter
than in summer) raising the value of the wind to the grid by
40 to 60 per cent, compared to a completely random wind pattern.
Having
said this, it should be added, that of course it is generally
an advantage to have a stable power output form a wind park.
At sea, periods of complete calm are generally extremely rare,
and quite short-lived. Thus the effective use of wind turbine
generating capacity will be higher at sea than on land.
2.3.
Huge Offshore Wind Resources
Offshore wind resources are enormous: Wind energy resources in
the seas of the European Union with water depths up to 50 metres
are easily several times larger than total European electricity
consumption.
The
offshore wind resource is obviously somewhat unevenly distributed
among countries. In the case of Denmark, offshore wind energy
may theoretically supply more than ten times national electricity
consumption, due to large areas with shallow waters (5 to 15
m depth).
2.4.
Low Surface Roughness: Cheaper Turbines
Another argument in favour of offshore wind power is the generally
smooth surface of water. This means that wind speeds do not increase
as much with the height above sea level as they do on land. This
implies that it may be economic to use lower (and thus cheaper)
towers for wind turbines located offshore.
2.5
Lower Turbulence: Longer Lifetime
The temperature difference between the sea surface and the air
above it is far smaller than the corresponding difference on
land, particularly during the daytime. This means that the wind
is less turbulent at sea than over land. This, in turn, will
mean lower mechanical fatigue load and thus longer lifetime for
turbines located at sea rather than land. No precise calculations
are as yet available, but we may guess at something like 25 to
30 year lifetime for a turbine with a design lifetime of 20 years
on land.
3.
The Challenges Offshore: Costs
The primary reason delaying offshore development of wind farms
has been cost. Although the price of wind turbines has been falling
some 20 per cent per kW installed power over the past three years,
and installation costs per kW installed on land have declined
due to upscaling of turbines, installation costs offshore have
remained more or less stable.
Foundations
and grid connection of large wind farms on land may be purchased
at a relatively modest cost of less than 60,000 ECU per wind
turbine (e.g. in the case of the Rejsby Hede wind farm in Denmark,
consisting of 39 wind turbines of 600 kW each). Foundations costs
were 6 per cent of project costs, while grid connection accounted
for 3 per cent.
Offshore,
however, foundations and cables add significantly to project
costs. In the latest Danish offshore wind farm at Tunoe Knob
(1995), for instance, wind turbines are placed at 5 to 10 metre
water depth. Here, foundation costs per turbine were at the level
of 23 per cent of project costs while grid connection costs were
around 14 per cent of project costs.
3.1
Economies of Scale
Economies of scale in the offshore wind energy area are two dimensional:
In terms of machine size, and in terms of number of units per
park.
3.1.1
Megawatt Turbine Size
Waves, and in some areas pack ice, are the most important factors
determining the required strength and weight of offshore foundations
for wind turbines. Consequently it is far more economic to use
larger wind turbines, since the size and costs of foundations
do not increase in proportion to the size of the wind turbine.
Another
important cost factor is grid connection. Here, it is obviously
far cheaper to attach fewer turbines to the grid for a given
wind farm size.
Larger
machines save money on maintenance, since the number of units
that have to be visited by boat will be smaller.
Megawatt-sized
wind turbines are now on the market, although not in large quantities,
as yet. The typical 1.5 to 1.65 megawatt machine has a 60 to
64 metre rotor diameter, and most of the Danish megawatt machines
were in fact designed with a view to offshore siting.
Further
upscaling of wind turbines is a possibility, although the logistics
of handling such large units on land have already become quite
difficult. Tower diameters should preferably not exceed 4.2 or
4.4 metres, if they are to be transported in normal sections
by road or rail.
Manufacturers
and customers alike would also like to use machines which have
been thoroughly tested on land, before moving out to sea.
3.1.2
Larger Wind Parks, up to 150 MW
The economically optimum size for an offshore wind park will
be significantly higher than on land. The cost of installing
an undersea 150 MW cable is not very different from the cost
of at 10 MW cable. Larger volume production of turbines and steel
foundations will also tend to decrease costs.
The
optimum size for an offshore park today appears to be around
120 to 150 MW. The upper limit is largely governed by the number
of sites which can be prepared for installation during a season
(summer half year) using a single sea crane and a limited number
of barges, diving crews etc. [1]
3.2
New Foundation Technologies
While economies of scale are important, the most interesting
breakthrough in offshore technology has been new engineering
studies done under the auspices of the Offshore Wind Turbine
Commission chaired by the Danish Energy Agency. Preliminary indications
point to a 35 per cent decrease in foundation costs, due to the
use of steel rather than concrete foundations. [2]
While
concrete platforms tend to become prohibitively heavy and expensive
to install at water depths above 10 metres, it appears that all
of the new technologies will be highly economic until at least
15 metres water depth, and possibly beyond such depths. In any
case, the marginal cost of moving into deeper waters is far smaller
than what was previously estimated.
Corrosion
protection of steel foundations can be done electrically, using
so called cathode protection requiring little or no human intervention
after the system is installed.
3.2.1
Gravity Foundations
The present offshore wind parks in Denmark are placed on reinforced
concrete foundations built onshore and floated out to sea where
they are filled with gravel and sand, much like traditional bridge
building technology. Such a foundation is known as a »gravity
foundation« since it relies on gravity to keep the turbine
in place.
One
of the newer technologies offers a similar method, but using
a cylindrical steel tube placed on a flat steel base on the bottom
of the sea. Such a foundation is considerably lighter, allowing
barges to transport and install many foundations rapidly, using
the same fairly lightweight crane used for the erection of the
turbines. These foundations are filled with olivine, a very heavy
mineral, which gives the foundation sufficient weight to withstand
waves and ice pressure.
3.2.2.
Mono Pile Foundations
Other foundation technologies include »mono pile«
foundations, effectively extending the turbine tower under water,
and drilling or ramming it into the sea bed. A pilot scheme with
five Danish wind turbines using this technology has been installed
south of the Swedish island of Gotland.
3.2.3.
Tripod Foundations
Finally, for larger water depths, three legged steel platforms
similar to offshore oil rigs are being studied. These foundations
have the advantage that they require less protection against
erosion than the other types of foundations, which generally
have to be protected by boulders (in sandy areas).
3.3
Reusing Foundations
While foundations are built to last 50 years, wind turbines are
presently built to last 20 years. With a somewhat larger expected
lifetime of, say 25 years, the same set of foundations can be
used for two successive generations of wind turbines. If the
foundations can thus be recycled, it may lower electricity generating
costs offshore by another 25-33 per cent, with costs roughly
achieving parity with typical onshore sites in Denmark.
3.4
Conclusions on Costs
Current studies of the kWh cost of energy from offshore wind
turbines in Denmark by the Danish utilities indicate a cost of
0.36 DKK/kWh = 0.05 USD/kWh using standard IEA calculation methods.
[1],[9] The calculations cautiously assume that present technologies
are used, and assume a 20 year lifetime.
If
we consider a 25 year lifetime, costs will be 9 per cent lower.
Danish
power companies (in their initial applications for planning permission)
have indicated that their projects require a 50 year design lifetime
for foundations, towers, main shafts, and the wind turbine nacelle
housing. If we assume a 50 year lifetime, with a very conservative
refurbishment cost equivalent to replacing the turbine itself
completely at present costs, then the energy price become 0.283
DKK/kWh = 0.04 USD/kWh.
These
costings include all installation and maintenance costs, including
grid reinforcement. The grid reinforcement component is quite
important in so far as it involves e.g. building 150 km of 400-600
kV power lines in the case of one of the larger park groups of
600-900 MW. [3]
4.
More Wind at Sea
The two Danish pilot offshore schemes have given very important
advances in the knowledge of the offshore environment.
Even
if higher wind speeds were expected at sea, the latest results
from Tunoe Knob indicate that offshore wind energy output is
20 to 30 per cent larger than forecasts made by traditional wind
modelling methods.
The
Risoe National Laboratory in Risoe, Denmark, which is known world-wide
for its WAsP wind modelling software, and the European Wind Atlas
[4], is in the process of revising its basic models after the
experience gained from Vindeby, Tunoe Knob, and four new offshore
meteorological masts erected in 1996.
It
appears that the wind shade effect from land obstacles such as
tall cliffs is more significant at sea than what the models say.
On the other hand, wind speeds farther offshore are higher than
model predictions.
A
research programme is currently in progress to improve offshore
wind modelling. The programme relies on improved data collection
from a number of offshore meteorology masts erected by the Danish
utility Elkraft.
5.
Offshore Turbine Design Modifications
The wind turbines used in the current offshore projects are largely
standard machines in the 450 kW to 600 kW range usually with
some additional corrosion protection. Gradually, interesting
modifications are beginning to appear, however.
Since
the beginning of offshore deployment, high voltage transformers
have of necessity been installed inside the wind turbine towers.
Other than better corrosion protection, this gives the additional
advantage of heating the equipment, thus avoiding cold starts
of the turbines.
At
Tunoe Knob, special electrical cranes were installed in each
turbine to allow replacement of even major components such as
rotor blades or generators without using a large and expensive
floating crane.
Another
interesting modification was a design change allowing a ten per
cent increase in rotor speed, increasing the effectiveness of
the turbines by some five to six per cent. Higher rotational
speed always carries a noise penalty, but as the theoretical
sound level on shore several kilometres away is minus 3 dB(A),
this is not a concern at all.
Finally,
the turbine manufacturers have taken a leaf out of the Navymen's
book: The turbines are painted in the standard NATO light grey
camouflage colour, and the rotor blade were manufactured in exactly
the same colour. The result is that even a slight amount of haze
makes the turbines disappear completely when viewed from the
shore.
6.
Park Operation, Logistics
Remote surveillance of offshore parks will obviously be even
more important than on land. Radio links for this purpose have
already been in operation at the Tunoe Knob and Vindeby offshore
wind parks for some years. With the large 1.5 MW units foreseen
for these parks, it may be economic to install e.g. extra vibration
sensors, a technology which is well known in industry to ensure
optimum maintenance of machinery.
Since weather conditions may prevent service personnel from
approaching the wind turbines at times of bad weather, it is
extremely important to ensure a high availability rate of offshore
wind turbines, (similar to the 98 to 99 per cent average achieved
by onshore turbines). Preventive maintenance check programmes
may need to be optimised for remote offshore locations.
7.
Environmental Impact of Offshore Wind Farms
7.1
Wildlife Considerations: Ducks don't Care
The Danish offshore projects have been very thoroughly researched
by biologists. At Vindeby test fishing was done in the area of
the wind turbines before they were built and after commissioning.
The
result was an surprising increase in fishing yields, attributable
to the fact that the turbines foundations appear as an artificial
stone reef. Mussels grow on the foundations of the turbines,
and the flora and fauna in the area have generally improved in
variety since the construction of the wind farm. There are few
birds at Vindeby, so no ornithology studies were feasible.
At
Tunoe Knob, however, a very extensive three year study was used
to determine the effects on the very large local population of
eiders (Somateria molissima). [5] The wind park was in fact located
in that very area at the request of researchers from the Danish
Environmental Agency, who wanted a testing ground with a large
bird population.
A
small observation platform with a cottage was placed on the sea
approximately one kilometre form the wind farm. Very extensive
observations from the tower have been performed, counting the
bird population, and studying flight behaviour. In addition,
aerial surveys have been used. Finally, divers have repeatedly
investigated the seabed for mussels, and using exclosures (wire
netting preventing bird access to certain areas of the seabed)
to be able to determine the feeding habits of the eiders. A nearby
control site with no wind turbines was used to determine the
effect of the wind farm.
The
result has been that the birds' presence is well correlated with
the presence of suitable food, but no statistically significant
impact on bird behaviour from the farm itself has been detected.
Bird studies will continue with the erection of future farms,
however, since different species of sea birds will be involved
7.2
CO2 and Global Energy Balance (Life Cycle) Considerations
Wind turbines generate no CO2, NOx or SOx during their operation,
and very little energy is required for the manufacture, maintenance
and scrapping of a wind power plant. In fact, with moderate wind
onshore sites, a wind turbine will recover all the energy spent
in its manufacture, installation and maintenance in less than
three months. With a 20 year lifetime that gives a thermal efficiency
(comparable to conventional power plant's 45 per cent) of no
less than 8,000 per cent!
For
offshore turbines the results may be better due to longer expected
lifetime of the turbines, cf. section 2.4 above. [6]
8.
Impact on the Future Electricity Supply System
8.1
Grid Integration
Grid connection of offshore wind parks is not a major technical
problem per se, in the sense that the technologies which are
involved are well known. Optimising these technologies for remote
offshore sites will be important, however, to ensure reasonable
economics.
The
first commercial-sized offshore wind farms in Denmark will be
located some 15-40 km (10-25 miles) from shore, at water depths
from 5 to 10, possibly 15 metres. The park sizes will range from
120 to 150 MW. The first parks (year 2000 or 2001) will be built
using the present 1.5 MW generation of wind turbines, which by
then will have been through an onshore operational period of
some five years.
Undersea
cabling connecting offshore parks to the main electrical grid
is a well known technology. Undersea cables will have to be buried
in order to reduce the risk of damage due to fishing equipment,
anchors, etc. If bottom conditions permit, it will be most economic
to wash cables into the seabed (using high pressure water jets)
rather than digging or ploughing cables into the bottom of the
sea.
Inside
the large 120-150 MW wind parks being planned in Denmark, it
is likely that 30-33 kV connections will be used. In the middle
of each park there will probably be a platform with a 30 to 150
kV transformer station, plus possibly a number of service facilities.
Connection to the mainland will be done using 150 kV connections.
Undersea
cables have a high electrical capacitance, which may be useful
to supply reactive power to the parks. It may be optimal to have
some form of variable reactive power compensation built into
the system, depending on the precise grid configuration. If the
distance to the main grid is considerable, an interesting alternative
could be to connect the parks to the mainland using high voltage
direct current connections (HVDC).
Total
generating capacity in Denmark was some 10,000 MW in 1998, including
1,000 MW of wind power. Introducing 4,000 MW of wind energy offshore,
plus another 1,000 MW onshore will change the very nature of
the present electricity supply system.
8.2
A Very Different Electricity Supply System
8.2.1 Plans for the Year 2030: 4000 MW Offshore
With 1,000 megawatts installed onshore (end 1997) Denmark already
covers more than seven per cent of its electricity consumption
from wind energy. Current plans envisage 1,500 megawatts onshore
by the year 2005, covering ten per cent of electricity consumption.
In
view of the rather optimistic conclusions above, the Danish government
is ordering the Danish electrical utilities to install 750 MW
wind power offshore, with the first park being commissioned around
year 2001. The Danish power companies are currently planning
very large wind farms of some 300 to 600 megawatts each, built
in modules of 120 to 150 megawatts, using 1.5 megawatt wind turbines.
Government
plans for the period until 2030, "Energy 21", envisage
a total of some 4,000 megawatts placed offshore, with wind covering
some 50 per cent of electricity consumption by 2030. [7]
8.2.2
Cheap CO2 Removal
The basic reason for installing such large amounts of wind power
is simple: Wind is a very inexpensive way of reducing CO2 emissions
cheaply. In fact, the Danish Energy Agency has calculated that
the social cost of saving one tonne of CO2 by switching from
modern coal fired power generation to wind has dropped from about
10 USD per tonne of CO2 in 1996 to zero today (not accounting
for environmental benefits). [8]
While these estimates were calculated on land-based wind turbines,
the cost per tonne of CO2 saved through the use of offshore turbines
is still slightly positive. Given current cost trends in the
industry, and the fact that cost estimates for future farms have
been largely based on current technology, it seems likely that
the excess cost of using wind power rather than coal will be
close to zero or negative in a few years time.
Wind Energy will account for more than a third of the CO2
emission reduction planned in Denmark for the year 2005 (7 out
of 20 per cent decline compared to 1988). In the future wind
will play an even larger role, according to current plans.
8.2.3
The Scandinavian Power Balance
Denmark currently has about 10,000 MW of installed electrical
generating capacity, and an annual electricity consumption of
around 31 TWh. The country is linked to both Germany, Sweden
and Norway. The links to Sweden and Norway, in particular, already
play an important role in balancing the electricity supply in
Scandinavia. Norway has a large, 99 per cent hydro-based system
with an annual production of some 120 TWh. In periods of drought,
Denmark's supplies large amounts of electricity to the other
countries, in other periods Denmark imports large amounts of
electricity.
With a total wind generating capacity of about 6,000 MW, There
will be lots of electricity available at periods of high winds.
During those periods, the Norwegian hydro system could effectively
be used for inexpensive energy storage, returning the current
later, during periods of relative calm weather. Thus, the combination
of wind and hydro are ideal, and would possibly enable larger
amounts of wind power to be installed in Danish waters.
8.2.4
Systems Design for Large Scale Introduction of Renewables
Large amounts of non-dispatchable renewables, such as wind, will
require an electricity system with far more decentralised power
generation, and with considerably more flexibility than the present
Danish electricity system.
Interestingly,
the general trend in Denmark is moving in that direction already,
due to a large scale conversion from large, centrally located
power plant to small, local gas fired CHP (combined heat and
power generating) plant. Heat storage plays an important role
in this system to allow a certain decoupling of heat and electricity
use, to ensure an economically and environmentally sound way
of running the system.
The
excess systems costs of introducing large amounts of renewables
in the grid in the years to come will be fairly reasonable, due
to the fact that the introduction is taking place in a planned
manner during a 40-year period during which most equipment would
be replaced anyway. The fascinating problems involved would merit
a separate paper, cf. the analysis by Risoe National Laboratory,
ELSAM and ELKRAFT in [9].
9.
Conclusions
9.1
Economic Benefits
Offshore wind energy is clearly an economically viable technology
for the 21st century. The present technology indicates generating
costs in the range of 4 to 5 US cents per kWh, according to IEA
standard methodology (on the basis of 120 to 150 MW projects
at water depths from 5 to 15 metres). Even without the environmental
benefits included, offshore wind energy is thus very close to
being competitive, both in comparison with onshore wind, and
in comparison with other generating technologies.
9.2
Environmental Benefits
Offshore wind energy can make a significant impact on the emission
problems related to conventional power generation technologies,
partly because the offshore wind resource base is huge, partly
because the technology is cost competitive.
The
Danish example shows, that costs of mitigating CO2 problems can
be brought down to a tolerable level. In fact, even though Denmark
has a 7 per cent wind energy penetration in the electrical grid,
electricity prices in Denmark (excluding indirect taxes) are
still among the very lowest in the European Union.
9.3
System Requirements
Large amounts of wind power will of course require a more flexible
electrical grid than what we know today, both in terms of handling
a fluctuating power input, and in terms of the flexibility of
other types of power plant (and possibly user load) in the system.
In cases where there is a possibility of combining hydro power
and wind, large scale introduction of wind would appear to be
a particularly attractive option, since hydro is the cheapest
form of electricity storage available.
9.4
Challenges
Offshore wind energy opens a new frontier of technological challenges.
Further upscaling of wind turbines, which are already the largest
rotating machinery on earth, will be a challenge to manufacturers.
Other challenges can be found in mass production of cheap foundations,
and improving the logistics of installation, surveillance, and
efficient maintenance.
Watch
the seas around Denmark a bit after the year 2000 to catch a
glimpse of the first commercial sized offshore wind farms in
Europe.
References
1. Elselskabernes og Energistyrelsens arbejdsgruppe for havmøller,
"Havmølle-handlingsplan for de danske farvande",
Danish Energy Agency, Copenhagen, 1997.
2. Elsamprojekt A/S, SEAS, LIC Engineering A/S, "Vindmøllefundamenter
i havet, slutrapport", Danish Energy Agency, Copenhagen,
1997.
3. Danish Wind Turbine Manufacturers Association web site,
www.windpower.org. The page http://www.windpower.org/tour/econ/offshore.htm
and the preceding calculator pages allow calculations of parameters
variations and sensitivity analysis on these calculations.
4. Ib Troen, Erik Lundtang Petersen, European Wind Atlas,
Risø National Laboratory, Risø, Denmark, 1989.
5. Magella Guillemette, Jesper Kyed Larsen, Ib Clausager,
"Effekt af Tunø Knob vindmøllepark på
fuglelivet", Faglig rapport fra DMU nr. 209, Danmarks Miljøundersøgelser,
Copenhagen, 1997.
6. Soren Krohn, "The Energy Balance of Modern Wind Turbines",
Wind Power Note no. 16, Danish Wind Turbine Manufacturers Association,
Copenhagen, 1997. (Web: http://www.windpower.org)
7. "Energy 21. The Danish Government's Action Plan for
Energy", Ministry of Environment and Energy, Copenhagen,
1996. (Web: http:// www.ens.dk)
8. "Danmarks Energifremtider", Ministry of Environment
and Energy, Copenhagen, 1997.
9. Lars Henrik Nielsen (ed.), "Vedvarende energi i stor
skala til el- og varmeproduktion", Risoe National Laboratory,
Risoe, Denmark, 1994.
10. John Olav Tande (ed.), "Estimation of Cost of Energy
from Wind Energy Conversion Systems", 2nd edition, IEA,
Risoe National Laboratory, 1994.
|